09 October 2026

Akaysha Energy welcomes AER approval of modified SIPS agreement as Waratah Super Battery reaches full operations

Aerial view of the Waratah BESS site with battery units and grid infrastructure.
Akaysha Energy has welcomed the Australian Energy Regulator's approval of the modified System Integrity Protection Scheme (SIPS) agreement for the Waratah Super Battery Project, marking a major milestone for the project and a nation-first demonstration of how large-scale battery storage can be structured to support a more reliable, flexible and affordable electricity system.

The approval follows the Waratah Super Battery achieving Final Commercial Operation Date (COD), with the 850 MW / 1,680 MWh battery now fully operational and delivering critical reliability services to the NSW electricity system.

The modified SIPS agreement, developed collaboratively by EnergyCo, Transgrid and Akaysha Energy, preserves the battery's role in delivering the 700MW SIPS service while enabling greater participation in the National Electricity Market when the service is not required. Importantly, profits generated through the battery's market participation will be shared with NSW electricity customers through a revenue-sharing arrangement, ensuring customers benefit from the additional flexibility.

The agreement is expected to increase the availability of dispatchable capacity, and improve market competition, while maintaining the security and reliability benefits the project was designed to deliver.

The modified SIPS arrangements are expected to commence in late 2026.

Paul Curnow, Chief Commercial Officer & Managing Director of Akaysha Energy, said the approval represented an important evolution in how grid-scale batteries can support both reliability and affordability.

"The Waratah Super Battery was built to strengthen the resilience of the NSW electricity system as the state transitions away from coal-fired generation. This approval ensures the battery will continue to deliver that critical reliability function while unlocking additional value for electricity customers."

"What makes this arrangement significant is that it enables the battery to support the grid when needed and participate in the market when it is not, improving utilisation of critical infrastructure without compromising system security."

"The modified agreement reflects strong collaboration between EnergyCo, Transgrid, the NSW Government and Akaysha Energy, and demonstrates how public and private sector partners can structure battery storage to support reliability, competition and better market outcomes. The Waratah Super Battery Project demonstrates a model with relevance well beyond NSW, offering important lessons for jurisdictions globally as they accelerate their own energy transition journeys."

The Waratah Super Battery Project helps maintain the reliability and security of the NSW electricity network as the state transitions away from coal-fired generation. The SIPS service acts as a network shock absorber, using a utility-scale battery, paired generation services and advanced control systems to respond rapidly to major network disturbances and help keep the power system stable.

If a major transmission fault occurs, the battery can rapidly discharge electricity into the grid while paired generators reduce output, helping avoid disruptions and allowing more electricity to be transferred across existing transmission lines to consumers in the Hunter, Sydney and Illawarra regions. The approved modifications ensure Transgrid's ability to reserve SIPS capacity can be reserved whenever required while improving utilisation of the battery when those services are not needed.

For Akaysha Energy, this approval and achievement of final COD represent the culmination of years of collaboration with EnergyCo, the NSW Government, Transgrid and project partners to deliver one of the most significant energy infrastructure projects in the state.